Image of the construction crew working on the new paved ramp (left) while a line of motorists forms on their way to Hwy 25. Image courtesy of VTA.
A construction crew works on the new paved ramp (left) while a line of motorists forms on the way to Hwy 25. Image courtesy of VTA.

Lea este artículo en español aquí.

Thousands of San Benito County residents who commute daily to Santa Clara County and other motorists who use the county’s heavily traveled thoroughfare will be routed to a temporary southbound Hwy 101 off-ramp toward Hwy 25 starting in December, Santa Clara County Valley Transportation Authority (VTA) Project Manager Karsten Adam. 

San Benito County announced motorists will begin using the new ramp on Dec. 10.

The temporary and extended off-ramp was recently paved and includes a traffic light at the Hwy 101/25 intersection. 

VTA will also shift traffic to a temporary on-ramp from northbound Hwy 25 to southbound Hwy 101.

Adam said PG&E is completing the traffic light’s electrical work. 

“There’s been a few delays on that,” he said at the Mobility Partnership meeting between the San Benito County Council of Governments and VTA on Nov. 18. 

He added that the current on- and off-ramps would be demolished after traffic is shifted to the new ramps. 

VTA is replacing the current interchange with a four-lane overcrossing, new and extended on- and off-ramps, a bike lane between Castro Valley Road and the interchange, and new traffic lights. 

The project also includes closing access to Mesa and Castro Valley roads from Hwy 101. 

According to the project website, the current overpass is more than 30 years old and cannot accommodate traffic demands “due to the rapid growth in commuter, commercial, and recreational traffic.”

The project, which is Phase 1 of a larger plan, is estimated to cost $136 million, with $76.8 million funded by Santa Clara County’s Measure B, approved in 2016, and the remaining $59.2 million through Senate Bill 1, VTA previously told BenitoLink.

According to the project website, future work includes transforming the interchange into a partial cloverleaf or diamond ramp. 

Image from VTA.

While VTA works on the interchange, it’s also conducting environmental studies to extend Hwy 25 to Santa Teresa Boulevard, considered Phase 2 of the overall plan for the area. The project is expected to be completed by 2031 and cost $50 million. 

Adam said the agency expects to move into the design phase next year and  right of way acquisition in 2028.

He said funding was secured to cover the environmental phase, and that the agency applied for $7 million in SB 1 monies, which includes a $3 million matching fund from VTA. 

“We’re hoping we get that grant,” he said, noting it’s the same grant VTA received for the first phase of this project. “We’lll find out in June 2027, so fingers crossed.”

The 101/25 interchange is part of a larger project which includes widening Hwy 101 from four to six lanes between Monterey Road and Hwy 129; building a bridge on Hwy 25 over the Union Pacific Railroad tracks; constructing a flood bridge west of the tracks and adding pedestrian and bike connections.

We need your help. Support local, nonprofit news! BenitoLink is a nonprofit news website covering San Benito County. Our team is committed to this community and to providing essential, accurate information to our fellow residents. Producing local news is expensive, and community support keeps the news flowing. Please consider supporting BenitoLink, San Benito County’s public service nonprofit news.